| NWTC
Certification Test Capabilities |

Certification Test Procedures
"Step-by-Step"
This section provides a step-by-step
outline for the certification process and, in particular, the process of planning,
performing, and reporting certification tests of a wind turbine generator. The links below
lead to more detailed information regarding each of the basic steps and procedures.
1. Investigate Certification Needs & Requirements
2. Certification Test Laboratory
3. Test Plan Development
4. Pre-test Preparation
5. Test Equipment Setup
- NWTC Test Equipment
- which instruments
- why needed
- where they go
- Company Equipment
- which instruments
- why needed
- where they go
6. Testing & Test Maintenance
- NWTC Test Program
- Collects data and informs company when finished
- Company Site Test
- visually inspects equipment daily
- downloads data weekly, sends to NREL
7. Test Report
- Company Role
- provides data and log sheets to NREL
- NWTC Role
- reviews company or NREL data
- writes certification test report (CTR)
- provides CTR to company
8. Certification
- Company sends report to certification agent
- Clarification Process
- Type
Certificate issued by certification agent
|